Oroville Spillway August 10, 2017

Published:

Progress is being made at the Lake Oroville Spillways around the clock. Crews continue to work day and night to clean and prepare the remaining rock, while rebar and stay-forms are placed where rock has already been prepared. Structural concrete is being poured in many sections of the upper and lower chute, and roller compacted concrete continues to be placed at night when temperatures are cooler.